[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389359,172,1,"单选题","一般，项目计划主要关注项目的活动计划，但是对大型复杂项目来说，必须优先考虑制定项目的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","活动计划",false,{"key":16,"text":17,"correct":18},"B","过程计划",true,{"key":20,"text":21,"correct":14},"C","资源计划",{"key":23,"text":24,"correct":14},"D","组织计划","某种意义上来说，一般项 目的计划主要关注的是项目活动的计划。但是对大型及复杂项目来说，制定活动计划之前，必须先考虑项目的过程计划，也就是必须先确定用什么方法和过程来完成项目。需不需要为一个项目单独建立一整套过程休系?这主要看过程木身的作用和项目本身的需求和特征。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]