[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389355,172,1,"单选题","为避免大型项目多个项目之间出现资源冲突，较有效的做法是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目开始实施时抢购一空资源在项目之间的分配原则，统一管理所有的项目和资源",false,{"key":16,"text":17,"correct":18},"B","定期检查项目的执行情况，根据项目进展情况和整体绩效重新排列项目的优先顺序，从资源上优先支持进展好的项目",true,{"key":20,"text":21,"correct":14},"C","将关键的子项目外包，提高项目整体绩效",{"key":23,"text":24,"correct":14},"D","项目实施初期投入少量资源，随着项目的进展不断增加相关资源","通过资源利用率（DIPP）来避免大型项目多个项目之间出现资源冲突是较为行之有效的办法。资源利用率（DIPP）等于项目期望货币值与完工尚需成本之比。资源利用率（DIPP） 值越高，意味着项目的资源利用率越高，越值得优先考虑。所以正确选项是B。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]