[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389326,172,1,"单选题","以下关于复杂项目管理的描述中，错误的是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","复杂的项目会遵循先自上而下后自下而上的计划制订过程",false,{"key":16,"text":17,"correct":14},"B","WBS的层级结构为认识、把握复杂项目的逻辑关系提供了良好的工具",{"key":19,"text":20,"correct":14},"C","一个复杂的项目往往有很多参与者，项目的顺利进展有赖于不同角色的协调工作",{"key":22,"text":23,"correct":24},"D","认知和协同环境必须意味着复杂项目的自动成功",true,"复杂项目的成功需要各个方面的管理成功，单单认知和协同环境不能是复杂项目自动成功。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]