[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389323,172,1,"单选题","围绕大型项目的目标管理，下列说法不正确的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大型项目的范围一般在启动时较难清晰确定",false,{"key":16,"text":17,"correct":18},"B","大型项目目标应关注“效果”，而不关注“效率”",true,{"key":20,"text":21,"correct":14},"C","大型项目目标要分解到各子项目和各部门",{"key":23,"text":24,"correct":14},"D","在项目各阶段往往要调整项目目标的优先次序","大型项目由于其复杂性，需求在项目初期是比较模糊的，因此，范围一般在启动时较难清晰确定。一般情况在确定项目目标时要从四个方面进行定义：范围、质量、进度和成本。范围和质量属于“效果”，而进度和成本属于“效率”。要保证目标能可控并实现就需要层层分解落实，并通过调整项目目标的优先次序来突出每个阶段的工作重点。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]