[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389321":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389321,172,1,"单选题","下列关于BPR的叙述中，（）是不正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","BPR需要对流程重新构思",false,{"key":16,"text":17,"correct":14},"B","BPR是对当前流程激进的破坏性创造",{"key":19,"text":20,"correct":21},"C","BPR是针对管理流程的重组",true,{"key":23,"text":24,"correct":14},"D","BPR有时会导致组织的不稳定","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]