[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389282,172,1,"单选题","在项目中实施变更应以 （ ） 为依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目干系人的要求",false,{"key":16,"text":17,"correct":14},"B","项目管理团队的要求",{"key":19,"text":20,"correct":21},"C","批准的变更请求",true,{"key":23,"text":24,"correct":14},"D","公司制度","在项目中实施变更应以“已批准的变更申请”为根据，更新相应基准计划，执行已批准的纠正措施即可。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]