[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389275,172,1,"单选题","当 （ ） 时，要正式通过变更审批。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.7版的项目管理计划调整",false,{"key":16,"text":17,"correct":14},"B","某活动在自由时差内的进度调整",{"key":19,"text":20,"correct":21},"C","某活动负责人要求进度提前",true,{"key":23,"text":24,"correct":14},"D","项目经理安排一次临时加班","变更审批前提是大事，一般指改变基线需要变更审批，0.7版的项目管理计划还处于草稿，没有形成基线，无需变更审批；自由时差内的进度调整不影响整个关键路径，没有更改进度基线，无需调整；临时加班不涉及基线更改，也不需变更审批；而进度提前，则属于进度基线改变，需要变更审批。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]