[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389274,172,1,"单选题","一项新的国家标准出台，某项目经理意识到新标准中的某些规定将导致其目前负责的一个项目必须重新设定一项技术指标，该项目经理首先应该 ：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","撰写一份书面的变更请求",true,{"key":16,"text":17,"correct":18},"B","召开一次变更控制委员会会议，讨论所面临的问题",false,{"key":20,"text":21,"correct":18},"C","通知受到影响的项目干系人将采取新的项目计划",{"key":23,"text":24,"correct":18},"D","修改项目计划和WBS，以保证该项目产品符合新标准","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]