[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389271":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389271,172,1,"单选题","在项目的实施阶段，当客户明确提出某项需求需要更改时，项目经理应该 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与客户方领导进行沟通，尽量劝说其不要更改需求",false,{"key":16,"text":17,"correct":18},"B","先评估变更会对项目带来怎样的影响，然后再与客户商量解决措施",true,{"key":20,"text":21,"correct":14},"C","接受客户的变更请求，启动变更控制流程，遵循变更流程进行更改",{"key":23,"text":24,"correct":14},"D","汇报给高层领导，由领导决定","在项目的实施阶段，当客户明确要变更时，项目经理应先评估变更会对项目带来怎样的影响，然后再与客户商量解决措施。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]