[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389260,172,1,"单选题","某大型项目的变更策略规定：把变更分为重大、紧急、一般和标准变更，并规定了不同级别的审批权限，比如重大变更由CCB审批，并规定标准变更属于预授权变更，可不用再走审批流程。此项目变更策略 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可行",false,{"key":16,"text":17,"correct":14},"B","不可行，主要是变更不能分级别，应统一管理",{"key":19,"text":20,"correct":21},"C","不可行，分四级可以，但审批都应由CCB批准",true,{"key":23,"text":24,"correct":14},"D","不可行，标准变更规定有问题","变更必须由CCB批准。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]