[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389256,172,1,"单选题","项目变更贯穿于整个项目过程的始终，项目经理应让项目干系人（特别是业主）认识到：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在项目策划阶段，变更成本较高",false,{"key":16,"text":17,"correct":14},"B","在项目执行阶段，变更成本较低",{"key":19,"text":20,"correct":14},"C","在项目编码开始前，变更成本较低",{"key":22,"text":23,"correct":24},"D","在项目策划阶段，变更成本较低",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]