[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389255,172,1,"单选题","在项目管理领域，经常把不受控制的变更称为项目“范围蔓延”。为了防止出现这种现象，需要控制变更。批准或拒绝变更申请的直接组织称为①，定义范围变更的流程包括必要的书面文件②和授权变更的批准等级；则正确的是 （ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①变更控制委员会；②纠正行动、跟踪系统",true,{"key":16,"text":17,"correct":18},"B","①项目管理办公室；②偏差分析、配置管理",false,{"key":20,"text":21,"correct":18},"C","①变更控制委员会；②偏差分析、变更管理计划",{"key":23,"text":24,"correct":18},"D","①项目管理办公室；②纠正行动、配置管理","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]