[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389254,172,1,"单选题","某项目已制定了详细的范围说明书，并完成了WBS 分解。在项目执行过程中，项目经理在进行下一周工作安排的时候，发现 WBS 中遗漏了一项重要的工作，那么接下来他应该首先 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织项目组讨论，修改WBS",false,{"key":16,"text":17,"correct":14},"B","修改项目管理计划，并重新评审",{"key":19,"text":20,"correct":14},"C","汇报给客户，与其沟通，重新编写项目文档",{"key":22,"text":23,"correct":24},"D","填写项目变更申请，对产生的工作量进行估算，等待变更委员会审批",true,"本题考查的是变更的流程，发生变更要按变更控制流程来进行。是最基本的知识，必须掌握。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]