[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389251":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389251,172,1,"单选题","项目组的测试人员在软件系统测试时发现了一个重大缺陷并报告给了项目经理，项目经理接下来应该（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提交一个变更申请",true,{"key":16,"text":17,"correct":18},"B","和质量保证人员商量如何修改",false,{"key":20,"text":21,"correct":18},"C","将任务分配给开发人员小王修改",{"key":23,"text":24,"correct":18},"D","评估是否需要修改","有重大缺陷一定需要修改，就涉本和资源，对项目正常运行会造成影响，所以要走变更控制流程，第一步是提交变更申请。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]