[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389246":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389246,172,1,"单选题","某软件开发项目计划设置如下基线：需求基线、设计基线、产品基线。在编码阶段，详细设计文件需要变更，以下叙述中， （ ） 是正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计文件评审已通过，直接变更即可",false,{"key":16,"text":17,"correct":14},"B","设计基线已经建立，不允许变更",{"key":19,"text":20,"correct":21},"C","设计基线已经建立，若变更必须走变更控制流程",true,{"key":23,"text":24,"correct":14},"D","详细设计与设计基线无关，直接变更即可","基线是一组经过正式审查并且达成一致的规范或工作产品，是开发工作的基础。对基线的更改必须遵循变更控制规程。 本题中的软件开发项目设置了需求基线、设计基线、产品基线，在编码阶段设计基线已经建立。若要对详细设计文件进行变更，必须走变更控制流程。故C是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]