[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389243,172,1,"单选题","配置项版本控制过程的步骤是（ ） 。①技术评审或领导审批②正式发布③修改处于“草稿”状态的配置项④创建配置项",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①④③②",false,{"key":16,"text":17,"correct":14},"B","③②①④",{"key":19,"text":20,"correct":21},"C","④③①②",true,{"key":23,"text":24,"correct":14},"D","④③②①","配置项版本控制过程的步骤是创建配置项、修改处于“草稿”状态的配置项、技术评审或领导审批、正式发布。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]