[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389227,172,1,"单选题","程序员小张在某项目中编写了源代码文件X的0.1版（以下简称Xv0.1）。随后的开发中小张又修改了Xv0.1，得到文件X的1.0版（以下简称Xv1.0）。经过正式评审后，Xv1.0被纳入基线进行配置管理。下列后续活动中符合配置管理要求的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","文件Xv1.0进入基线后，配置管理员小李从配置库中删除了文件Xv0.1",false,{"key":16,"text":17,"correct":18},"B","程序员小张被赋予相应的权限，可以直接读取受控库中的文件Xv1.0",true,{"key":20,"text":21,"correct":14},"C","小张直接对Xv1.0进行了变更，之后通知了项目经理",{"key":23,"text":24,"correct":14},"D","经过变更申请、变更评估并决定实施变更后，变更实施人完成了变更，随后立即发布了变更，在第一时间内将变更内容和结果通知所有相关人员","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]