[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389216,172,1,"单选题","某软件开发项目的需求规格说明书第一次正式发布，命名为《需求规格说明书 V1.0》，此后经过两次较小的升级，版本号升至 V1.2，此时客户提出一次需求变更，项目组接受了变更，按客户的要求对需求规格说明书进行了较大的改动并通过评审，此时版本号应升级为 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","V1.3",false,{"key":16,"text":17,"correct":14},"B","V1.5",{"key":19,"text":20,"correct":21},"C","V2.0",true,{"key":23,"text":24,"correct":14},"D","V3.0","配置项版本格式X.Y，如果改动较小则增大Y值；如果有较大修改，则增大X值。题目中，项目进行了较大的改动并通过评审。所以版本号应升级为V2.0。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]