[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389182,172,1,"单选题","基线由一组配置项组成，这些配置项构成了一个相对稳定的逻辑实体，是一组经过（ ） 正式审查、批准、达成一致的范围或工作产品 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","用户",false,{"key":16,"text":17,"correct":14},"B","配置管理员",{"key":19,"text":20,"correct":21},"C","配置控制委员会",true,{"key":23,"text":24,"correct":14},"D","专家组","配置管理计划的主要内容包括配置管理软硬件资源、配置项计划、基线计划、交付计划、备份计划等。由配置控制委员会审批该计划。主要属性有:名称、标识符、文件状态、版本、作者、日期等",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]