[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389162,172,1,"单选题","某项目已经按照沟通计划发布了项目信息，此时一些项目可交付成果按照变更控制计划发生了变更，并向所有干系人都发出了变更通知。而项目后期一位干系人表示对该变更并不知情。此时，该项目的项目经理首先应 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对沟通计划进行审核，如需要，对沟通计划进行修改",true,{"key":16,"text":17,"correct":18},"B","审核沟通计划，确定为什么干系人不理解自己的职责",false,{"key":20,"text":21,"correct":18},"C","确定为什么该干系人不知情",{"key":23,"text":24,"correct":18},"D","在下次筹划委员会会议上说明该 问题，以便其他干系人不会遗忘公布的变更信息","从题干很明显可以看出，沟通计划有遗漏，因此正确答案为选项A。这个考察的就是沟通处理的流程，有人对沟通不满意项目经理首先要审查沟通管理计划。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]