[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389158,172,1,"单选题","沟通管理计划包括确定项目干系人的信息和沟通需求，在编制沟通计划时，（）不是沟通计划编制的输入。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织过程资产",false,{"key":16,"text":17,"correct":14},"B","项目章程",{"key":19,"text":20,"correct":21},"C","沟通需求分析",true,{"key":23,"text":24,"correct":14},"D","项目范围说明书","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]