[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389152,172,1,"单选题","以下关于项目沟通管理的叙述中，不正确的是：（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对于大多数项目而言，沟通管理计划应在项目初期就完成",false,{"key":16,"text":17,"correct":14},"B","基本的项目沟通内容信息可以从项目工作分解结构中获得",{"key":19,"text":20,"correct":21},"C","制定合理的工作分解结构与项目沟通是否充分无关",true,{"key":23,"text":24,"correct":14},"D","项目的组织结构在很大程度上影响项目的沟通需求","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]