[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389145":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389145,172,1,"单选题","下面关于沟通管理计划的说法中，不正确的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","沟通管理计划应是正式的，根据项目需要可以是非常详细或粗略框架式的",true,{"key":16,"text":17,"correct":18},"B","沟通管理计划确定了项目干系人的信息和沟通要求",false,{"key":20,"text":21,"correct":18},"C","沟通管理计划不一定需要得到客户的正式认可才能实施",{"key":23,"text":24,"correct":18},"D","沟通管理计划中应包含用于沟通的信息，包括信息格式、内容和细节水平","沟通管理计划根据项目需要可以是正式或非正式的，非常详细地或粗略的框架式的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]