[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389144,172,1,"单选题","两名新成员最近加入到某项目中，项目组成员原来有6个人，则沟通途径增加了（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":18},"B","13",true,{"key":20,"text":21,"correct":14},"C","12",{"key":23,"text":24,"correct":14},"D","8","沟通渠道=N（N?1）\u002F2，N表示沟通的人数；原先沟通渠道=6（6?1）\u002F2=15；两名新成员加入后沟通渠道=8（8?1）\u002F2=28；28?15=13，所以沟通途径增加了13。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]