[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389135,172,1,"单选题","项目经理小王负责某项目管理，考虑到项目人力资源紧张，就与三个在校学生签订了临时劳务合同，并允许这三名在校学生可以利用互联网进行办公，同时规定每周三上午这些学生必须参与团队的工作会议。以下针对上述情况的观点中，正确的是（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","三名学生不属于项目团队成员",false,{"key":16,"text":17,"correct":18},"B","项目经理小王组建了虚拟项目团队",true,{"key":20,"text":21,"correct":14},"C","三名学生不可以参加团队的工作会议",{"key":23,"text":24,"correct":14},"D","项目经理小王利用了谈判技术来组建团队","学生利用互联网办公属于虚拟团队办公范畴。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]