[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389093":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389093,172,1,"单选题","（）不是组建项目团队的工具和技术。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事先分派",false,{"key":16,"text":17,"correct":18},"B","资源日历",true,{"key":20,"text":21,"correct":14},"C","采购",{"key":23,"text":24,"correct":14},"D","虚拟团队","组建项目团队的工具和技术有事先分派、谈判、采购和虚拟团队。 资源日历不属于组建项目团队的工具和技术。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]