[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389068,172,1,"单选题","某项目质量管理的部分流程为：编制需求报告→编制测试计划→测试设计→批准测试设计→ 测试→编制测试报告→批准测试报告。新入职的测试人员小刘按照该流程对某系统进行了测试并产生了测试报告，客户对测试内容和结果不满意。该项目质量管理中存在的最主要问题是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测试人员素质不高",false,{"key":16,"text":17,"correct":14},"B","测试用例设计方法不当",{"key":19,"text":20,"correct":21},"C","缺少评审环节",true,{"key":23,"text":24,"correct":14},"D","缺少质量审计环节","通过阶段性的评审可以保证项目的质",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]