[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389057,172,1,"单选题","以下关于项目质量控制的叙述中， （ ） 是不正确的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目质量控制是一种预防性、提高性和保障性的质量管理活动",true,{"key":16,"text":17,"correct":18},"B","项目质量控制是一种过程性、纠偏性和把关性的质量管理活动",false,{"key":20,"text":21,"correct":18},"C","项目调整和变更是项目质量控制的一种阶段性和整体性的结果",{"key":23,"text":24,"correct":18},"D","项目质量的事前控制主要是对于项目质量影响因素的控制","预防性、提高性和保障性的质量管理活动应该是质量保证。质量保证和质量控制，在具体项目活动中比较容易混淆，考生应注意到，质量保证是预防性的，是提前的；质量控制是纠正性的，是过程中的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]