[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389054,172,1,"单选题","某项目经理在制定项目质量计划时，从客户对项目交付物的质量要求出发，先识别客户在功能方面的要求，然后把功能要求与产品的特性对应起来，形成功能要求与产品特性的关系矩阵，进而确定产品的技术参数。他采用的方法是 ：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量成本分析",false,{"key":16,"text":17,"correct":14},"B","效益\u002F成本分析",{"key":19,"text":20,"correct":21},"C","质量功能展开",true,{"key":23,"text":24,"correct":14},"D","过程决策程序图法","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]