[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389051,172,1,"单选题","在进度管理中常用的活动网络图，如计划评审技术（PERT）、关键路径法等，也可以应用于质量管理的（ ）过程中",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","规划质量管理",false,{"key":16,"text":17,"correct":14},"B","实施质量保证",{"key":19,"text":20,"correct":21},"C","质量控制",true,{"key":23,"text":24,"correct":14},"D","质量改进","根据《系统集成项目管理工程师教程（第2版）》第368页，质量控制的新七工具中，包括了活动网络图，如计划评审技术（PERT）、关键路径法（CPM）和紧前关系绘图法（PDM）。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]