[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389050,172,1,"单选题","甲公司承担的某系统开发项目，在进入开发阶段后，出现了一系列质量问题。为此，项目经理召集项目团队，列出问题，并分析问题产生的原因。结果发现，绝大多数的问题都是由几个原因造成的，项目组有针对性地采取了一些措施。这种方法属于_____ 法。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因果图",false,{"key":16,"text":17,"correct":14},"B","控制图",{"key":19,"text":20,"correct":21},"C","排列图",true,{"key":23,"text":24,"correct":14},"D","矩阵图","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]