[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389049,172,1,"单选题","（ ） 是编制质量规划的首要工作",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","寻找影响质量的因素",false,{"key":16,"text":17,"correct":14},"B","研究项目产品说明书",{"key":19,"text":20,"correct":14},"C","确定质量度量指标",{"key":22,"text":23,"correct":24},"D","识别相关质量标准",true,"质量规划，重要的是识别每一个独特项目的相关质量标准，把满足项目相关质量标准的活动或者过程规划到项目的产品和管理项目所涉及的过程中去。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]