[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389028,172,1,"单选题","在某信息化项目建设过程中，客户对于最终的交付物不认可，给出的原因是系统信号强度超过用户设备能接受的上限。请问在项目执行过程中，如果客户对于项目文件中的验收标准无异议，则可能是 ______环节出了问题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量控制",true,{"key":16,"text":17,"correct":18},"B","WBS分解过程",false,{"key":20,"text":21,"correct":18},"C","变更控制",{"key":23,"text":24,"correct":18},"D","范围确认","如果客户对于项目文件中的验收标准有异议，即对工作结果是否能够接受存在异议，这属于范围控制环节的问题。 再例如： 倘若客户对项目文件中的验收标准无异议，但存在问题的环节在于对工作结果是否达到验收标准(即正确与否)的认定，则属于质量控制环节。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]