[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389016,172,1,"单选题","下表是项目甲、乙、丙三个项目的进度数据，则（ ）最有可能在成本的约束内完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目甲",true,{"key":16,"text":17,"correct":18},"B","项目乙",false,{"key":20,"text":21,"correct":18},"C","项目丙",{"key":23,"text":24,"correct":18},"D","项目甲和项目丙","EV(甲）\u002FPV（甲）=8000\u002F15000 1; EV(乙）\u002FPV（乙）=5000\u002F15000\u003C1,EV(乙)\u002FAC(乙）=5000\u002F8000\u003C1; EV(丙）\u002FPV（丙）=8000\u002F15000\u003C1,EV(丙)\u002FAC(丙）=8000\u002F9000\u003C1;计算甲最优。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]