[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389012,172,1,"单选题","某项目包含 A、 B、C三项主要活动，项目经理在成本估算时采用自下而上的方法，分别估算出三项活动的成本分别为13万元，23万元和8万元，同时为了应对未来可能遇到的不确定因素，预留了10万元的管理储备，同时为每个活动预留了2万元的准备金。该项目的总预算为（57）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","44",false,{"key":16,"text":17,"correct":14},"B","54",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","46","总预算直接相加。13+23+8+10+6=60 这里要注意的是管理储备是项目预算的一部分，但不是成本基准的一部分，所以不纳入挣值计算。 典型情况下ETC=（BAC-EV）\u002FCPI=(50-50*30%)\u002F50*30%\u002F20=46.7",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]