[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389009,172,1,"单选题","根据下图，表示竣工费用超支情况的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①",true,{"key":16,"text":17,"correct":18},"B","②",false,{"key":20,"text":21,"correct":18},"C","③",{"key":23,"text":24,"correct":18},"D","④","①：CV=EV-AC＜0，成本超支； ②：CV=EV-AV＜0，成本超支；③：SV=EV-PV＞0，进度超前；④：SV=EV-PV＜0，进度滞后。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]