[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389004,172,1,"单选题","对于系统集成企业而言，在进行项目核算时，一般将 （ ） 列入项目生命周期间发生的直接成本。 ①可行性研究费用 ②项目投标费用 ③监理费用 ④需求开发费用⑤设计费用 ⑥实施费用 ⑦验收费用",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②④⑤⑥⑦",false,{"key":16,"text":17,"correct":14},"B","①③④⑤⑥⑦",{"key":19,"text":20,"correct":21},"C","④⑤⑥⑦",true,{"key":23,"text":24,"correct":14},"D","②④⑤⑥⑦","项目生命周期包括启动、计划、执行、收尾四个阶段。本题中这四个阶段中发生的直接成本包括需求开发费用、设计费用、实施费用、验收费用。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]