[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389001":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389001,172,1,"单选题","成本基准是用来度量与检测项目成本绩效的按时间分配预算，下图中给出了某项目期望现金流、成本基准、资金需求情况，图中区间A应为 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管理储备",true,{"key":16,"text":17,"correct":18},"B","成本偏差",false,{"key":20,"text":21,"correct":18},"C","进度偏差",{"key":23,"text":24,"correct":18},"D","超出成本","最大资金需求和成本基准末端值的差异就是管理储备。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]