[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388999,172,1,"单选题","以下关于成本估算的说法错误的是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本一般用货币单位（人民币、美元、欧元、日元）来表示",false,{"key":16,"text":17,"correct":14},"B","针对项目使用的所有资源来估算计划活动成本",{"key":19,"text":20,"correct":21},"C","一般不考虑关于风险应对方面的信息",true,{"key":23,"text":24,"correct":14},"D","估算完成每项计划活动所需的资源的近似成本","成本估算人员应考虑有关风险的因素，因为风险的应对措施需要成本，风险也几乎总是增加成本和延迟进度。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]