[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388998":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388998,172,1,"单选题","某个项目的预算是3000万元，工期为5个月，现在过去了3个月，实际成本1800万元，项目进度和绩效都符合计划，而且这种情况也会持续下去，则再过3个月，项目的EV是（45）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1800",false,{"key":16,"text":17,"correct":14},"B","2400",{"key":19,"text":20,"correct":14},"C","1200",{"key":22,"text":23,"correct":24},"D","3000",true,"再过3个月项目的EV是1800+1200=3000万元。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]