[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388994":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388994,172,1,"单选题","某项目计划分为立项、实施和运维三个阶段。财务部给该项目的预算金额不超过80万元。项目经理估算立项阶段的成本为20万元，实施阶段的成本为50万元，运维阶段的成本为30万元。若用自底向上法对该项目的成本进行估算，则估算值应为 （ ） 万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","70",false,{"key":16,"text":17,"correct":14},"B","80",{"key":19,"text":20,"correct":14},"C","90",{"key":22,"text":23,"correct":24},"D","100",true,"自底向上法，就是先估算单个工作包的成本，然后将这些详细成本汇总得到更高层的成本。所以将立项、实施和运维三个阶段成本相加就得到项目估算值，该值为100。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]