[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388993,172,1,"单选题","下表为同时开展的4个项目在某个时刻的计划值PV、实际成本AC和挣值EV，该时刻成本超出最多的项目和进度最为落后的项目分别是_____。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目1，项目1",false,{"key":16,"text":17,"correct":14},"B","项目3，项目2",{"key":19,"text":20,"correct":21},"C","项目4，项目4",true,{"key":23,"text":24,"correct":14},"D","项目2，项目4","根据公式CV=EV-AC，SPI=EV\u002FPV，可以计算出4个项目的CV、SPI如下： 4个项目中，具有最小CV值的项目为项目4，表示项目4成本超出最多。4个项目中具有最小SPI值的项目为项目4",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]