[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388991,172,1,"单选题","项目每个阶段结束时的一个重要工作是进行项目绩效评审，评审的主要目标是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","决定项目是否能够进入下一个阶段",true,{"key":16,"text":17,"correct":18},"B","根据过去的绩效调整项目的进度和成本基准",false,{"key":20,"text":21,"correct":18},"C","评定员工业绩和能力",{"key":23,"text":24,"correct":18},"D","得到客户对项目绩效认同","评审的目的主要是决定项目是否能够进入下一个阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]