[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388989,172,1,"单选题","下图是一项布线工程计划和实际完成的示意图，2009年3月23日的PV、EV、AC分别是 ：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","PV=4000元、EV=2000元、AC=3800元",true,{"key":16,"text":17,"correct":18},"B","PV=4000元、EV=3800元、AC=2000元",false,{"key":20,"text":21,"correct":18},"C","PV=3800元、EV=4000元、AC=2000元",{"key":23,"text":24,"correct":18},"D","PV=3800元、EV=3800元、AC=2000元","从图中可以看出，截止到3.23日的PV=2000+2000=4000EV=2000 AC=3800 因此答案A正确",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]