[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388981":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388981,172,1,"单选题","项目成本控制是指 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对成本费用的趋势及可能达到的水平所做的分析和推断",false,{"key":16,"text":17,"correct":14},"B","预先规定计划期内项目施工的耗费和成本要达到的水平",{"key":19,"text":20,"correct":14},"C","确定各个成本项比预计要达到的目标成本的降低额和降低度",{"key":22,"text":23,"correct":24},"D","在项目过程中，对形成成本的要素进行监督和调节",true,"本题考查的是成本控制的定义，最基本的知识，需要掌握。凡是看到“控制”二字，都要知道，控制不仅仅是监督、分析、判断，还要调节、调整、改进等。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]