[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388976,172,1,"单选题","为工作包建立控制账户，并根据“账户编码”分配标记号是创建工作分解结构的最后步预。控制账户 （ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不是构成汇总成本、进度和资源信息的单元",false,{"key":16,"text":17,"correct":18},"B","是一种控制点，项目的范围、成本和进度在该点被整合",true,{"key":20,"text":21,"correct":14},"C","是设置在工作分解结构的特定技术节点",{"key":23,"text":24,"correct":14},"D","只包括一个工作包","控制账户，简称CA，是一种管理控制点，是工作包的规划基础。在该控制点上，把范围、成本和进度加以整合，并把它们与挣值相比较，以测量绩效。控制账户设置在工作分解结构中的特定管理节点上。每一个控制账户都可以包括一个或多个工作包，但是每一个工作包只能属于一个控制账户。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]