[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388973,172,1,"单选题","项目进行到某阶段时，项目经理进行了绩效分析，计算出CPI值为0.91。这表示：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目的每91元人民币投资中可创造相当于100元的价值",false,{"key":16,"text":17,"correct":14},"B","当项目完成时将会花费投资额的91%",{"key":19,"text":20,"correct":14},"C","项目仅进展到计划进度的91%",{"key":22,"text":23,"correct":24},"D","项目的每100元人民币投资中只创造相当于91元的价值",true,"由题干得知CPI=0.91\u003C1 说明项目的成本超支，同时，也表明项目每100元人民币投资中只创造了相当于91元的价值因此，选项D正确",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]