[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388972,172,1,"单选题","某信息系统集成项目的预算为5050000元，工期6周。某时间点，该项目花了1550000元完成了预计要花1690000元的工作，而计划成本是2110000元。则该项目的实际成本 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","低于预算",true,{"key":16,"text":17,"correct":18},"B","超出预算",false,{"key":20,"text":21,"correct":18},"C","符合预算",{"key":23,"text":24,"correct":18},"D","提供的信息不足，无法判断","AC=1550000，EV=1690000，PV=2110000，CV（成本偏差）=EV-AC＞0，表示成本节约。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]