[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388970,172,1,"单选题","项目经理在运行预算方案编制时，收集到的基础数据如下：工作包的成本估算为40万元；工作包的应急储备金为4万元；管理储备金为2万元。该项目的成本基准是（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","40",false,{"key":16,"text":17,"correct":18},"B","44",true,{"key":20,"text":21,"correct":14},"C","42",{"key":23,"text":24,"correct":14},"D","46","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]