[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388968":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388968,172,1,"单选题","项目经理刚刚完成一个小项目的启动阶段，开始步入计划编制阶段，这时，公司主管经营的副总经理向项目经理索要项目预算和成本基准计划。该项目经理较恰当的回答是（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可以在项目章程中找到项目预算，项目章程刚刚做完",false,{"key":16,"text":17,"correct":18},"B","在计划编制阶段完成之前，项目预算和基准计划是不能最终确定的",true,{"key":20,"text":21,"correct":14},"C","项目计划将不包括项目预算和基准计划，这是个小项目",{"key":23,"text":24,"correct":14},"D","在制订项目计划之前不可能完成估算","计划编制常用的技术就是渐进明细。在美国项目管理协会PMI编制的PMBOK中，指在项目进程中，随着信息越来越详细，估算越来越准确，持续改进和细化计划。所以在计划编制阶段完成之前，项目预算和基准计划是不能最终确定的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]